[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269772,857,1,"单选题","施工项目成本控制的步骤是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","比较一分析一预测一纠偏一检查",true,{"key":16,"text":17,"correct":18},"B","预测一比较一分析一纠偏一检查",false,{"key":20,"text":21,"correct":18},"C","比较一分析一预测一检查一纠偏",{"key":23,"text":24,"correct":18},"D","预测一分析一比较一纠偏一检查","施工项目成本控制的步骤：比较一分析一预测一纠偏一检查。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]