[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269770":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269770,857,1,"单选题","在施工成本控制的步骤中，通过（ ），可以估算整个项目完成时的施工成本，为决策提供支持。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预测",true,{"key":16,"text":17,"correct":18},"B","检查",false,{"key":20,"text":21,"correct":18},"C","分析",{"key":23,"text":24,"correct":18},"D","比较","在施工成本控制的步骤中，通过预测，可以估算整个项目完成时的施工成本，为决策提供支持。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]