[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1269769,857,1,"单选题","对项目目标进行动态跟踪和控制，在确定了项目目标计划值后的施工过程中，首先应做的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整项目目标",false,{"key":16,"text":17,"correct":14},"B","采取纠偏措施进行纠偏",{"key":19,"text":20,"correct":21},"C","收集工程进度的实际值",true,{"key":23,"text":24,"correct":14},"D","比较项目目标的实际值与计划值","对项目目标进行动态跟踪和控制，在确定了项目目标计划值后的施工过程中，首先应做的是收集工程进度的实际值。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]