[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269766":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269766,857,1,"单选题","具有形象直观，但反映的信息量少，一般在项目的较高管理层应用的施工成本偏差分析方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图法",true,{"key":16,"text":17,"correct":18},"B","表格法",false,{"key":20,"text":21,"correct":18},"C","排列法",{"key":23,"text":24,"correct":18},"D","曲线法","横道图比较法是指将在项目实施中检查实际进度收集的信息，经整理后直接用横道线并列标于原计划的横道线处，进行直观比较的方法。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]