[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269758,857,1,"单选题","未搞清地质情况就仓促开工，边设计边施工，无图施工，不经竣工验收就交付使用等，这是施工项目质量问题中（ ）的原因。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","违背建设程序",true,{"key":16,"text":17,"correct":18},"B","违反法规行为",false,{"key":20,"text":21,"correct":18},"C","地质勘察失真",{"key":23,"text":24,"correct":18},"D","施工与管理不到位","建设程序是指工程项目从策划、评估、决策、设计、施工到竣工验收、投入生产或交付使用的整个建设过程，促开工，边设计边施工，无图施工，不经竣工验收就交付使用等违背了建设程序。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]