[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269746":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269746,857,1,"单选题","在工程验收过程中，经具有资质的法定检测单位对个别检验批检测鉴定后，发现其不能够达到设计要求。但经原设计单位核算后认为能满足结构安全和使用功能的要求。对此，正确的做法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可予以验收",true,{"key":16,"text":17,"correct":18},"B","禁止验收",false,{"key":20,"text":21,"correct":18},"C","由建设单位决定是否通过验收",{"key":23,"text":24,"correct":18},"D","需要返工","在工程验收过程中，对于某质量不符合要求的工程，经具有资质的法定检测单位对个别检验批检测鉴定后，发现其能够达到设计要求，应该可予以验收",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]