[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269744":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269744,857,1,"单选题","某工程项目，在确定工期目标后，为保证项目按期完成，项目经理进一步确定了每月的进度目标。这项工作在运用动态控制原理进行进度控制的工作步骤中，属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将工程进度目标逐层分解",true,{"key":16,"text":17,"correct":18},"B","定期比较工程进度的实际值与计划值",false,{"key":20,"text":21,"correct":18},"C","收集工程进度实际值",{"key":23,"text":24,"correct":18},"D","确定进度控制周期","对于特大型工程项目,应先编制施工总进度规划、使进度目标逐层分解和细化。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]