[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269743":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1269743,857,1,"单选题","合同控制的技术措施主要包括：（ ）。①采用多级网络计划技术和其他先进适用的计划技术②加强合同管理，加强组织、指挥和协调，以保证合同进度目标的实现③严格控制合同变更，对各方提出的工程变更和设计变更，经监理工程师严格审查后补进合同文件④采用先进高效的技术和设备⑤加强风险管理，在合同中要充分考虑风险因素及其对进度的影响和处理办法",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①③⑤",false,{"key":16,"text":17,"correct":18},"B","②③⑤",true,{"key":20,"text":21,"correct":14},"C","③④⑤",{"key":23,"text":24,"correct":14},"D","①④⑤","合同控制的技术措施主要包括：加强合同管理，加强组织、指挥和协调，以保证合同进度目标的实现；严格控制合同变更，对各方提出的工程变更和设计变更，经监理工程师严格审查后补进合同文件；加强风险管理，在合同中要充分考虑风险因素及其对进度的影响和处理办法。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]