[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269740":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1269740,857,1,"单选题","下列不属于施工项目管理任务的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工安全管理",false,{"key":16,"text":17,"correct":14},"B","施工质量控制",{"key":19,"text":20,"correct":21},"C","施工人力资源管理",true,{"key":23,"text":24,"correct":14},"D","施工合同管理","施工项目管理任务是施工安全管理、施工质量、控制管理、施工合同管理。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]