[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269739":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1269739,857,1,"单选题","某建设工程项目经理部根据目标动态控制原理，将项目目标进行了分解，那么在项目目标实施过程中，首先应进行的工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确定目标控制的计划值",false,{"key":16,"text":17,"correct":14},"B","定期比较目标的计划值与实际值",{"key":19,"text":20,"correct":14},"C","分析比较结果，采取纠偏措施",{"key":22,"text":23,"correct":24},"D","收集目标的实际完成值",true,"建设工程项目经理部根据目标动态控制原理，将项目目标进行了分解，在项目目标实施过程中，首先应进行的工作是收集目标的实际完成值。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]