[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1269738,857,1,"单选题","一般情况下，不管采取哪些措施，都会（ ）费用。因此，在调整施工进度计划时应利用费用优化的原理选择费用（ ）的关键工作作为压缩对象。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","减少，增加最少",false,{"key":16,"text":17,"correct":14},"B","增加，减少最少",{"key":19,"text":20,"correct":21},"C","增加，增加最少",true,{"key":23,"text":24,"correct":14},"D","减少，增加最多","一般情况下，不管采取哪些措施，都会增加费用。因此，在调整施工进度计划时应利用费用优化的原理选择费用增加最少的关键工作作为压缩对象。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]