[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269727":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1269727,857,1,"单选题","施工项目成本控制的方法中，偏差分析可采用不同的方法，常用的有横道图法、（ ）和曲线法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","比率法",false,{"key":16,"text":17,"correct":18},"B","表格法",true,{"key":20,"text":21,"correct":14},"C","比较法",{"key":23,"text":24,"correct":14},"D","差额法","施工项目成本控制的方法中，偏差分析可采用不同的方法，常用的有横道图法、表格法和曲线法。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]