[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269684":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1269684,857,3,"判断题","主排水沟最好设置在施工区域的边缘或道路的两旁，一般排水沟的横断面不应小于0.5m×0.5m，纵向坡度不应小于2‰。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"主排水沟最好设置在施工区域的边缘或道路的两旁，其横断面和纵向坡度应根据当地气象资料，按照施工期内最大流量确定。但排水沟的横断面不应小于0.5m×0.5m，纵向坡度不应小于2‰。",{"id":6,"name":21,"category":22,"favorite":23},"(土建质量)基础知识","建筑工程",0]