[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269682,857,1,"单选题","土方的开挖顺序、方法必须与设计工况相一致，并遵循开槽支撑，（ ）严禁超挖的原则。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先撑后挖，分层开挖",true,{"key":16,"text":17,"correct":18},"B","先挖后撑，分层开挖",false,{"key":20,"text":21,"correct":18},"C","先撑后挖，分段开挖",{"key":23,"text":24,"correct":18},"D","先挖后撑，分段开挖","土方的开挖顺序、方法必须与设计工况相一致，并遵循开槽支撑，先撑后挖，分层开挖，严禁超挖的原则。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]