[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269668":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1269668,857,3,"判断题","一般抹灰施工的顺序应遵循“先室内后室外、先上后下、先墙地后顶棚”的原则。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"一般抹灰施工的施工顺序应遵循“先室外后室内、先上后下、先顶棚后墙地”的原则。",{"id":6,"name":21,"category":22,"favorite":23},"(土建质量)基础知识","建筑工程",0]