[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269630":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269630,857,1,"单选题","下列关于预制桩施工的基本规定，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","静力压桩不宜用于地下有较多孤石、障碍物或有4m以上硬隔离层的情况",true,{"key":16,"text":17,"correct":18},"B","如遇特殊原因，压桩时可以不连续进行",false,{"key":20,"text":21,"correct":18},"C","静力压桩的施工工艺流程：测量放线→桩机就位、吊桩、插桩、桩身对中调直→静压沉桩→接桩→送桩、再静压沉桩→终止压桩→切割桩头",{"key":23,"text":24,"correct":18},"D","送桩时必须采用送桩器","静力压桩不宜用于地下有较多孤石、障碍物或有4m以上硬隔离层的情况。静力压桩的施工工艺流程：测量放线→桩机就位、吊桩、插桩、桩身对中调直→静压沉桩→接桩→再静压沉桩→送桩、终止压桩→切割桩头。压桩时应连续进行。送桩时可不采用送桩器，只需用一节长度超过要求送桩深度的桩放在被送桩顶上便可送桩，送桩深度不宜超过8m。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]