[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1269579,857,1,"单选题","观察验槽的重点应选择在（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基坑中心线",false,{"key":16,"text":17,"correct":14},"B","基坑边角处",{"key":19,"text":20,"correct":21},"C","受力较大的部位",true,{"key":23,"text":24,"correct":14},"D","最后开挖的部位","应重点观察柱基、墙角、承重墙下或其他受力较大部位",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]