[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269302":3},{"question":4,"library":19},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":9},1269302,856,3,"判断题","顶管顶进工作井进人土层，每顶进300mm，测量不应少于一次；正常顶进时，每顶进1000mm，测量不应少于一次。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,{"id":6,"name":20,"category":21,"favorite":22},"(市政质量)专业管理实务 岗位知识","建筑工程",0]