[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269132":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1269132,856,3,"判断题","钢筋安装位置与预应力管道或锚件位置发生冲突时，可适当调整预应力管道的位置，确保钢筋安装位置准确。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"钢筋安装位置与预应力管道或锚件位置发生冲突时：适当调整钢筋位置，确保预应力管道位置符合设计要求。",{"id":6,"name":21,"category":22,"favorite":23},"(市政质量)专业管理实务 岗位知识","建筑工程",0]