[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269068":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1269068,856,2,"多选题","某工程竣工时，施工单位经过初验，认为已按合同约定的要求完成施工，提请作竣工验收，由于场地狭小，施工单位仍占用部分房屋作为办公用房，根据对竣工验收资料的要求，施工单位已将全部质量保证资料复印齐全供审核。经质量监督站初步抽验，观感、质量得分率为83％。质量保证资料未能通过，并提出了整改通知单。根据背景资料，回答以下问题： 建设单位收到工程竣工报告后，对符合竣工验收要求的工程，组织（ ）等单位组成验收组，制定验收方案。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","材料供应商",false,{"key":16,"text":17,"correct":18},"B","勘察",true,{"key":20,"text":21,"correct":18},"C","设计",{"key":23,"text":24,"correct":18},"D","施工",{"key":26,"text":27,"correct":18},"E","监理","BCDE","建设单位收到工程竣工报告后，对符合竣工验收要求的工程，组织勘察、设计、施工、监理等单位组成验收组，制定验收方案。",{"id":6,"name":31,"category":32,"favorite":33},"(市政质量)专业管理实务 岗位知识","建筑工程",0]