[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269065":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1269065,856,2,"多选题","施工完成的雨污水管道在回填前应该按照设计及规范要求进行闭水试验，试验结果由（ ）等参与各方签字确认。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","质监站",false,{"key":16,"text":17,"correct":18},"B","业主",true,{"key":20,"text":21,"correct":18},"C","监理",{"key":23,"text":24,"correct":14},"D","勘察",{"key":26,"text":27,"correct":18},"E","设计","BCE","教材255",{"id":6,"name":31,"category":32,"favorite":33},"(市政质量)专业管理实务 岗位知识","建筑工程",0]