[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269041":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1269041,856,2,"多选题","下列属于预防管道铺设偏差的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","在管道铺设前，必须对管道基础仔细复核，复核轴线位置、线形以及标高是否与设计标高吻合",true,{"key":16,"text":17,"correct":14},"B","稳管用垫块应事前按施工方案预制成形，安放位置准确",{"key":19,"text":20,"correct":14},"C","管道铺设操作应从下游向上游敷设，承口向上，切忌倒向排管",{"key":22,"text":23,"correct":14},"D","采取边线控制排管时所设边线应紧绷，防止中间下垂；采取中心线控制排管时应在中间铁撑柱上画线，将引线扎牢，防止移动，并随时观察，防止外界扰动",{"key":25,"text":26,"correct":14},"E","每节（根）管应先用样尺与样板架观察校验，然后再用水准尺检（试）验落水方向","ABCDE","预防管道铺设偏差：在管道铺设前，必须对管道基础仔细复核，复核轴线位置、线形以及标高是否与设计标高吻合；稳管用垫块应事前按施工方案预制成形，安放位置准确；管道铺设操作应从下游向上游敷设，承口向上，切忌倒向排管；采取边线控制排管时所设边线应紧绷，防止中间下垂；采取中心线控制排管时应在中间铁撑柱上画线，将引线扎牢，防止移动，并随时观察，防止外界扰动；每节（根）管应先用样尺与样板架观察校验，然后再用水准尺检（试）验落水方向；在管道铺设前，必须对样板架再次测量复核，符合设计高程后开始稳管。",{"id":6,"name":30,"category":31,"favorite":32},"(市政质量)专业管理实务 岗位知识","建筑工程",0]