[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269011":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1269011,856,2,"多选题","无压管道闭水试验的叙述正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","试验管段灌满水后浸泡时间不少于24h",true,{"key":16,"text":17,"correct":18},"B","试验管段灌满水后浸泡时间不少于12h",false,{"key":20,"text":21,"correct":14},"C","试验水头达规定水头时开始计时，观测管道的渗水量，直至观测结束时，应不断地向试验管段内补水，保证试验水头恒定",{"key":23,"text":24,"correct":14},"D","渗水量的观测时间不得小于30min",{"key":26,"text":27,"correct":18},"E","渗水量的观测时间不得小于60min","ACD","无压管道闭水试验（1）试验管段灌满水后浸泡时间不少于24h;（2）试验水头应按上述要求确定；（3）试验水头达规定水头时开始计时，观测管道的渗水量，直至观测结束时，应不断地向试验管段内补水，保证试验水头恒定：渗水量的观测时间不得小于30min。（4）判断标准按《给水排水管道工程施工及验收规范》GB50268—2008有关要求对排水管道有关检测进行判定。",{"id":6,"name":31,"category":32,"favorite":33},"(市政质量)专业管理实务 岗位知识","建筑工程",0]