[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268951":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1268951,856,2,"多选题","属于施工项目质量计划编制的方法的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","材料设备质量管理及措施",true,{"key":16,"text":17,"correct":14},"B","工程检测项目方法及控制措施",{"key":19,"text":20,"correct":21},"C","施工工艺过程的控制",false,{"key":23,"text":24,"correct":21},"D","安装和调试的过程控制",{"key":26,"text":27,"correct":21},"E","材料与机械设备的检测","AB","“施工工艺过程的控制”和“安装和调试的过程控制”属于质量计划的编制要求。",{"id":6,"name":31,"category":32,"favorite":33},"(市政质量)专业管理实务 岗位知识","建筑工程",0]