[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1268914,856,1,"单选题","单位工程质量竣工验收记录中施工单位由（ ）签字确认。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","项目副经理",{"key":19,"text":20,"correct":14},"C","项目总工",{"key":22,"text":23,"correct":24},"D","单位负责人",true,"单位工程质量竣工验收记录中施工单位由单位负责人签字确认。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]