[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268859":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1268859,856,1,"单选题","某主干道污水管道工程，设计采用直径700mm的HDPE高密度聚乙烯双壁波纹管。在沟槽开挖中，由于施工员未交代清楚，结果槽底挖深了20cm左右，施工员发现后，立即安排用挖出的土回填至设计高程。管道工程施工完毕后不到一个月发生沟槽位置沉陷，经查管道内部无明显问题。管道使用一年多时间后，发现有检查井四周沉降，井盖破损，管道塌瘪现象，造成排水不畅，需要返工。 规范规定：沟槽胸腔及管顶以上（ ）范围内填土时，应做到分层回填，两侧同时进行回填夯实，高差不得超过30cm,回填土中不得含有碎石、石块及大于10cm冻土块，管座混凝土强度达5MPa以上方能回填。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30cm",false,{"key":16,"text":17,"correct":14},"B","40cm",{"key":19,"text":20,"correct":21},"C","50cm",true,{"key":23,"text":24,"correct":14},"D","60cm","规范规定：沟槽胸腔及管顶以上50cm范围内填土时，应做到分层回填，两侧同时进行回填夯实，高差不得超过30cm,回填土中不得含有碎石、石块及大于10cm冻土块，管座混凝土强度达5MPa以上方能回填。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]