[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268854":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1268854,856,1,"单选题","管道铺设偏差的原因分析不包括。（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管道轴线线形不直，又未予纠正",false,{"key":16,"text":17,"correct":14},"B","标高测放误差，造成管底标高不符合设计要求",{"key":19,"text":20,"correct":14},"C","稳管垫块放置的随意性，使用垫块与施工方案不符，致使管道铺设不稳定，接口不顺，影响流水畅通",{"key":22,"text":23,"correct":24},"D","承插管未按承口向下游、插口向上游的安放规定",true,"管道铺设偏差的原因：管道轴线线形不直，又未予纠正；标高测放误差，造成管底标高不符合设计要求；稳管垫块放置的随意性，使用垫块与施工方案不符，致使管道铺设不稳定，接口不顺，影响流水畅通",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]