[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1268846,856,1,"单选题","建设方或监理工程师在施工单位通知检验后（ ）h内未能进行检验，则视为建设方和监理检验合格，承包商有权覆盖并进行下一道工序。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",true,{"key":16,"text":17,"correct":18},"B","24",false,{"key":20,"text":21,"correct":18},"C","36",{"key":23,"text":24,"correct":18},"D","48","建设方或监理工程师在施工单位通知检验后12h内未能进行检验，则视为建设方和监理检验合格，承包商有权覆盖并进行下一道工序。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]