[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1268842,856,1,"单选题","一般项目的质量经抽样检验合格；当采用计数检验时，除有专门要求外，一般项目的合格点率应达到（ ）及以上，且不合格点的最大偏差值不得大于规定允许偏差的（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","70％，1.2",false,{"key":16,"text":17,"correct":14},"B","80％，1.2",{"key":19,"text":20,"correct":14},"C","70％，1.5",{"key":22,"text":23,"correct":24},"D","80％，1.5",true,"一般项目的质量经抽样检验合格；当采用计数检验时，除有专门要求外，一般项目的合格点率应达到80％及以上，且不合格点的最大偏差值不得大于规定允许偏差的1.5。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]