[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268840":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1268840,856,1,"单选题","隐蔽工程完工后，应及时进行隐蔽工程验收，作为（ ）验收的依据。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单位工程",false,{"key":16,"text":17,"correct":14},"B","子单位工程",{"key":19,"text":20,"correct":14},"C","分部工程",{"key":22,"text":23,"correct":24},"D","分项工程",true,"隐蔽工程完工后，应及时进行隐蔽工程验收，作为分项工程验收的依据。其他工序工程完工后，虽然不单独进行验收，但应及时将与质量相关的情况记人施工记录中，作为分项工程（或检验（收）批）质量验收的依据。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]