[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1268838,856,1,"单选题","下列不属于隐蔽工程的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","道路基层",false,{"key":16,"text":17,"correct":14},"B","钢筋工程",{"key":19,"text":20,"correct":21},"C","道路面层",true,{"key":23,"text":24,"correct":14},"D","管道铺设","隐蔽工程是指那些在施工过程中上一道工序的工作结束，被下一道工序所掩盖，而无法进行复查的部位。例如地下管线的铺设、道路基层、结构钢筋混凝土工程的钢筋（埋件）等。隐蔽工程验收通常是结合质量控制中技术复核、质量检查工作来进行，重要部位改变时可摄影以备查考。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]