[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268810":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1268810,856,1,"单选题","采用低应变法、高应变法和声波透射法抽检桩身完整性所发现的Ⅲ、IV类桩之和大于抽检桩数的（ ）时，宜采用原检测方法（声波透射法可改用钻芯法），在未检桩中继续扩大抽检。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10％",false,{"key":16,"text":17,"correct":14},"B","15％",{"key":19,"text":20,"correct":21},"C","20％",true,{"key":23,"text":24,"correct":14},"D","25％","采用低应变法、高应变法和声波透射法抽检桩身完整性所发现的Ⅲ、IV类桩之和大于抽检桩数的20%时，宜采用原检测方法（声波透射法可改用钻芯法），在未检桩中继续扩大抽检。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]