[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268790":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1268790,856,1,"单选题","根据GB50204-2002（2011年版）要求，进场钢筋必须进行钢筋重量偏差检测，测量钢筋重量偏差时，试样应从不同钢筋上截取，每根试样长度不小于（ ）mm。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","100",false,{"key":16,"text":17,"correct":14},"B","300",{"key":19,"text":20,"correct":14},"C","350",{"key":22,"text":23,"correct":24},"D","500",true,"根据GB50204-2002（2011年版）要求，进场钢筋必须进行钢筋重量偏差检测，测量钢筋重量偏差时，试样应从不同钢筋上截取，每根长度不小于500mm。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]