[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1268752,856,1,"单选题","根据GB50204-2002（2011年版）要求，进场钢筋必须进行钢筋重量偏差检测。测量钢筋重量偏差时，试样应从不同钢筋上截取，数量不少于（ ）根。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","9","根据GB50204-2002（2011年版）要求，进场钢筋必须进行钢筋重量偏差检测。测量钢筋重量偏差时，试样应从不同钢筋上截取，数量不少于5根。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]