[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268743":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1268743,856,1,"单选题","箱梁支架预压的目的不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检验支架的强度及稳定性",false,{"key":16,"text":17,"correct":18},"B","消除地基的弹性变形",true,{"key":20,"text":21,"correct":14},"C","测量出支架的弹性变形",{"key":23,"text":24,"correct":14},"D","为调整支架标高提供依据","箱梁支架预压的目的：检验支架的强度及稳定性，消除整个支架的塑性变形，消除地基的沉降变形，测量出支架的弹性变形，为调整支架标高提供依据。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]