[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268715":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1268715,856,1,"单选题","预应力筋张拉，实际伸长值与理论伸长值的差值应符合设计要求；设计未规定时，实际伸长值与理论伸长值之差应控制在（ ）以内。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4%",false,{"key":16,"text":17,"correct":18},"B","6%",true,{"key":20,"text":21,"correct":14},"C","8%",{"key":23,"text":24,"correct":14},"D","10%","预应力筋张拉，实际伸长值与理论伸长值的差值应符合设计要求；设计未规定时，实际伸长值与理论伸长值之差应控制在6%以内。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]