[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1268704,856,1,"单选题","预应力筋的张拉顺序应符合设计要求，当设计无规定时（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","宜先中间，后上、下或两侧",true,{"key":16,"text":17,"correct":18},"B","宜先两侧，后上、下或中间",false,{"key":20,"text":21,"correct":18},"C","宜先上、下，后中间或两侧",{"key":23,"text":24,"correct":18},"D","宜同时进行","预应力筋的张拉顺序应符合设计要求，当设计无规定时宜先中间，后上、下或两侧",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]