[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268694":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1268694,856,1,"单选题","单位工程、分部工程和分项工程开工前，（ ）应向承担施工的负责人或分包人进行书面技术交底。技术交底资料应办理签字手续并归档。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","公司技术负责人",{"key":19,"text":20,"correct":21},"C","项目技术负责人",true,{"key":23,"text":24,"correct":14},"D","质量员","单位工程、分部工程和分项工程开工前，项目技术负责人应向承担施工的负责人或分包人进行书面技术交底。技术交底资料应办理签字手续并归档。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)专业管理实务 岗位知识","建筑工程",0]