[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268549":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1268549,855,3,"判断题","粉喷桩加固施工工艺为：原地面整平→测量放样→钻机定位钻杆下沉钻进→上提搅拌复搅下沉→复搅喷粉提升→成桩钻机移位。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"粉喷桩加固施工工艺为：原地面整平—测量放样—钴机定位—钻杆下沉钻进—上提喷粉强制搅拌-复搅下沉—复搅喷粉提升—成粧钻机移位。",{"id":6,"name":21,"category":22,"favorite":23},"(市政质量)基础知识","建筑工程",0]