[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268291":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1268291,855,2,"多选题","模板、支架和拱架拆除应按设计要求的程序和措施进行，遵循（ ）的原则。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先支先拆",false,{"key":16,"text":17,"correct":18},"B","先支后拆",true,{"key":20,"text":21,"correct":14},"C","后支后拆",{"key":23,"text":24,"correct":18},"D","后支先拆",{"key":26,"text":27,"correct":14},"E","边支边拆","BD","模板、支架和拱架拆除应按设计要求的程序和措施进行，遵循“先支后拆、后支先拆”的原则。",{"id":6,"name":31,"category":32,"favorite":33},"(市政质量)基础知识","建筑工程",0]