[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268273":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1268273,855,2,"多选题","下列关于石灰土基层施工中有误的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","路拌法采用塑性指数小的黏土时，第一次加70%～100%预定剂量的石灰进行拌合，闷放1～2d，此后补足需用的石灰，再进行第二次拌合",true,{"key":16,"text":17,"correct":14},"B","路拌法碾压应在最佳含水量时进行，先12t压路机稳压，整形后一般采用8t以上压路机碾压",{"key":19,"text":20,"correct":21},"C","路拌法施工间断或分段施工时，交界处预留300～500mm不碾压，便于新旧料衔接",false,{"key":23,"text":24,"correct":14},"D","厂拌法石灰土铺摊长度约100m时宜在最佳含水量时进行碾压，试碾压后及时进行高程复核",{"key":26,"text":27,"correct":21},"E","厂拌法碾压原则上以“先慢后快”、“先轻后重”、“先低后高”为宜","ABD","路拌法采用塑性指数大的黏土时，第一次加70%～100%预定剂量的石灰进行拌合，闷放1～2d，此后补足需用的石灰，再进行第二次拌合。路拌法碾压应在最佳含水量时进行，先用8t压路机稳压，整形后一般采用12t以上压路机碾压。路拌法施工间断或分段施工时，交界处预留300～500mm不碾压，便于新旧料衔接。厂拌法石灰土铺摊长度约50m时宜在最佳含水量时进行碾压，试碾压后及时进行高程复核。厂拌法碾压原则上以“先慢后快”、“先轻后重”、“先低后高”为宜。",{"id":6,"name":31,"category":32,"favorite":33},"(市政质量)基础知识","建筑工程",0]