[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1268063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1268063,855,1,"单选题","施工单位应当在施工组织设计中编制安全技术措施和施工现场临时用电方案，达到一定规模的危险性较大的分部分项工程编制专项施工方案，并附安全验算结果，（ ）、总监理工程师签字后实施。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位负责人",false,{"key":16,"text":17,"correct":14},"B","施工单位负责人",{"key":19,"text":20,"correct":14},"C","施工单位项目经理",{"key":22,"text":23,"correct":24},"D","施工单位技术负责人",true,"经施工单位技术负责人、总监理工程师签字后实施，由专职安全生产管理人员进行现场监督。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]