[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267937":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1267937,855,1,"单选题","下列不属于施工项目目标控制的任务有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","质量目标控制",false,{"key":16,"text":17,"correct":14},"B","进度目标控制",{"key":19,"text":20,"correct":14},"C","成本目标控制",{"key":22,"text":23,"correct":24},"D","安全目标控制",true,"施工项目目标控制的任务主要有质量目标控制、进度目标控制和成本目标控制。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]