[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267929":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1267929,855,1,"单选题","下列不属于运用动态控制原理控制施工成本的步骤有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工成本目标的制定",true,{"key":16,"text":17,"correct":18},"B","施工成本目标的逐层分解",false,{"key":20,"text":21,"correct":18},"C","在施工过程中，对施工成本目标进行动态跟踪和控制",{"key":23,"text":24,"correct":18},"D","调整施工成本目标","运用动态控制原理控制施工成本的步骤（1）施工成本目标的逐层分解。（2）在施工过程中，对施工成本目标进行动态跟踪和控制。（3）调整施工成本目标。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]