[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267883":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1267883,855,1,"单选题","已知沉井下沉施工过程中工人8h换班一次，某班组于8：30时（24小时制）换班，则该班组对沉井的高程、轴线位移进行了测量的最迟时间是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","12：30",false,{"key":16,"text":17,"correct":14},"B","14：30",{"key":19,"text":20,"correct":21},"C","16：30",true,{"key":23,"text":24,"correct":14},"D","18：30","沉井下沉监控测量：（1）下沉时高程、轴线位移每班至少测量一次，每次下沉稳定后应进行高差和中心位移量的计算。（2）终沉时，每小时测一次，严格控制超沉，沉并封底前自沉速率应小于10mm\u002F8h。（3）如发生异常情况应加密量测。（4）大型沉井应进行结构变形和裂缝观测。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]