[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267861":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1267861,855,1,"单选题","下列有关人工拆除桥梁的说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","作业人员应站在稳定的结构或脚手架上操作.被拆除的构件放置在周围",false,{"key":16,"text":17,"correct":14},"B","人工拆除施工应从上至下、逐层拆除、分段进行.可以交叉垂直作业",{"key":19,"text":20,"correct":14},"C","人工拆除挡土墙时.可直接采用掏掘或推倒的方法",{"key":22,"text":23,"correct":24},"D","拆除梁或悬挑构件时.应采取有效的下落控制措施.方可切断两端的支撑",true,"A。选项中被拆除的构件要有安全的放置场所；B选项中不可交叉垂直作业；C选项中，人工拆除挡土墙时不可采用掏掘或推倒的方法。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]