[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1267827,855,1,"单选题","绘水排水压力管道的水压试验分为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","强度试验和严密性试验",false,{"key":16,"text":17,"correct":18},"B","预试验和主试验",true,{"key":20,"text":21,"correct":14},"C","闭水试验和闭气试验",{"key":23,"text":24,"correct":14},"D","满水试验和严密性试验","本题考点涉及给水排水压力管道的水压试验的内容。给水排水压力管道内水压缓慢地升至规定的试验压力并稳压30min，期间如有压力下降可注水补压，补压不得高于试验压力；检查管道接口、配件等处有无漏水、损坏现象；有漏水、损坏现象时应及时停止试压，查明原因并采取相应措施后重新试压。主试验阶段停止注水补压，稳定15min；15min后压力下降不超过所允许压力下降数值时，将试验压力降至工作压力并保持恒压30min，进行外观检查若无漏水现象，则水压试验合格。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]