[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267782":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1267782,855,1,"单选题","下列选项中，不属于施工项目管理组织的内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织系统的设计与建立",false,{"key":16,"text":17,"correct":18},"B","组织沟通",true,{"key":20,"text":21,"correct":14},"C","组织运行",{"key":23,"text":24,"correct":14},"D","组织调整","施工项目管理组织，是指为进行施工项目管理、实现组织职能而进行组织系统的设计与建立、组织运行和组织调整三个方面。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]