[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267768":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1267768,855,1,"单选题","下列不属于在项目实施过程中项目目标的动态控制内容的有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","收集项目目标的实际值，如实际投资、实际进度等",false,{"key":16,"text":17,"correct":14},"B","定期（如每两周或每月）进行项目目标的计划值和实际值的比较",{"key":19,"text":20,"correct":21},"C","不定期（如每两周或每月）进行项目目标的计划值和实际值的比较",true,{"key":23,"text":24,"correct":14},"D","通过项目目标的计划值和实际值的比较，如有偏差，则采取纠偏措施进行纠偏","在项目实施过程中项目目标的动态控制：收集项目目标的实际值，如实际投资、实际进度等；定期（如每两周或每月）进行项目目标的计划值和实际值的比较；通过项目目标的计划值和实际值的比较，如有偏差，则采取纠偏措施进行纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]