[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267755":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1267755,855,1,"单选题","土工合成材料膨润土垫（GCI）施工必须在（ ）进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","有水的地面上",false,{"key":16,"text":17,"correct":14},"B","下雨时",{"key":19,"text":20,"correct":21},"C","平整的土地上",true,{"key":23,"text":24,"correct":14},"D","有一定坡度的路面上","土工合成材料膨润土垫，简称GCL。GCL施工必须在平整的土地上进行；对铺设场地条件的要求比土工膜低。GCL之间的连接以及GCL与结构物之间的连接都很简便，并且接缝处的密封性也容易得到保证。GCL不能在有水的地面及下雨时施工，在施工完后要及时铺设其上层结构如HDPE膜等材料。大面积铺设采用搭接形式，不需要缝合，搭接缝应用膨润土防水浆封闭。对GCI.出现破损之处可根据破损大小采用撒膨润土或者加铺GCL方法修补。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]